Answered by:
Why is the Sprint Burndown report not showing To Do tasks?

Question
-
Why is the Sprint Burndown report not showing To Do tasks?
I'm not seeing anything in the Sprint Burndown report for the current sprint.
Nearly all Tasks have State of To Do. and all have estimates.
All the Task also have Iteration set to the current sprint.
The Sprint is also setup to start today.
The previous sprint currently shows the Done items only and not the To Dos but this could be correct (but this does prove that the reports are picking up some data)http://learnerps-dotnet.blogspot.com
- Moved by Jack Zhai-MSFTMicrosoft contingent staff Friday, June 8, 2012 8:09 AM It is related to the TFS-Reporting. (From:Getting Started With Visual Studio Team System)
Thursday, June 7, 2012 11:08 AM
Answers
-
By default the warehouse is updated every 2 minutes and the cube is updated every 2 hours. These settings can be changed. Read more at http://msdn.microsoft.com/en-us/library/ms244694.aspx
Further more SSRS by default caches report results. Read more at http://msdn.microsoft.com/en-us/library/ms157146.aspx .
So it can take some hours before your reports actually show the data entered in your work items...
Also, I believa all reports in TFS aggregate data on a day to day basis so a burndown chart wont show anything during the first day, basically because there is not enough data to generate the report.
- Proposed as answer by Lily_WuModerator Wednesday, June 13, 2012 2:26 AM
- Marked as answer by learnerplates Thursday, June 14, 2012 3:33 PM
Tuesday, June 12, 2012 10:42 AM
All replies
-
As far as I can remember you need to put a number in the "time remaining" field for the tasks to show up in the burndown. Putting a number in the "original estimate" field does nothing for the burndown chart.
You can read up on the burndown chart here: http://msdn.microsoft.com/en-us/library/dd380678
Thursday, June 7, 2012 2:00 PM -
As far as I can remember you need to put a number in the "time remaining" field for the tasks to show up in the burndown. Putting a number in the "original estimate" field does nothing for the burndown chart.
You can read up on the burndown chart here: http://msdn.microsoft.com/en-us/library/dd380678
We have filled in Estimated Effort and Remaining Work in all our Tasks. but still no sign of the illusive To Dos.
http://learnerps-dotnet.blogspot.com
Thursday, June 7, 2012 2:07 PM -
Hi learnerp,
I am moving your thread into the Team Foundation Server - Reporting & Warehouse Forum for dedicated support. Thanks for your understanding.
Best Regards,
Jack Zhai [MSFT]
MSDN Community Support | Feedback to us
Friday, June 8, 2012 8:08 AM -
Which process template is your Team Project based on?Friday, June 8, 2012 9:20 AM
-
Hi learnerplates,
Thank you for your post.
How about the issue now?
If anything is unclear, please free feel to let me know.
Best Regards,
Lily Wu [MSFT]
MSDN Community Support | Feedback to us
Monday, June 11, 2012 8:46 AMModerator -
I've checked this today and it's now working, miraculously.
Is there a delay between the the data the report uses and the actual data warehouse? maybe it takes a full day or so before it shows in the report, I see the x-axis is in 5day intervals!
http://learnerps-dotnet.blogspot.com
Tuesday, June 12, 2012 9:47 AM -
By default the warehouse is updated every 2 minutes and the cube is updated every 2 hours. These settings can be changed. Read more at http://msdn.microsoft.com/en-us/library/ms244694.aspx
Further more SSRS by default caches report results. Read more at http://msdn.microsoft.com/en-us/library/ms157146.aspx .
So it can take some hours before your reports actually show the data entered in your work items...
Also, I believa all reports in TFS aggregate data on a day to day basis so a burndown chart wont show anything during the first day, basically because there is not enough data to generate the report.
- Proposed as answer by Lily_WuModerator Wednesday, June 13, 2012 2:26 AM
- Marked as answer by learnerplates Thursday, June 14, 2012 3:33 PM
Tuesday, June 12, 2012 10:42 AM