Set Default PDP page's Project RRS feed

  • Question

  • I use Project Server 2013. As I know when I click project name on project center, it navigate to PDP that I just open before close this project.

    Can I set default or force PDP page  like project schedule for everybody see this PDP when they back to project.

    Cloud anybody have solution for this?    

    Thank you :) 

    Monday, June 17, 2013 8:33 AM

Answers

All replies

  • The last viewed PDP is persisted per user rather than per project. So each user will see the last PDP that was loaded by him/herself.


    www.umt.com

    Monday, June 17, 2013 4:02 PM
  • So Can't I change or custom this setting?
    Tuesday, June 18, 2013 3:34 AM
  • Hi 

    You can modify existing EPT or create new the EPT (Enterprise project type) and add your custom PDP in the PDP section. Ensure that your PDP is top in the order . The PDP will be shown. In PDP you can use the Project Server WebPart to display the necessary information.

    Enjoy..


    .NET developre

    Thursday, August 22, 2013 3:17 PM