Unable to set Project Start Date from PSI RRS feed

  • Question

  • Hi,

    I am creating a project using PSI. After creating the project using PSI, i am also updating the Project Start Date using PSI.

    However, the Project Start Date is not getting set. The project is being created with an EPT that has a Project Plan Template associated with it. The task in Project Plan Template have an earlier start date than the Start date set. Hence, the Project Start date is not applied.

    I am looking for ways to set the Project Start date and have the Task dates updates based on the Start Date set. However, I am unable to do it from PSI. Any help in this regard will be appreciated.

    Sunday, December 21, 2014 12:37 PM

All replies

  • To further clarify, the Start Date of the project is set from the Project Start Date in Project plan Template. I would like the Project Start Date to be set by the PSI code, not by template.

    Sunday, December 21, 2014 1:17 PM