How To Migrate Reports from Project 2010 to Project 2013 ? RRS feed

  • Question

  • I need to migrate automatically (or at least semi-automatically) about 50 (non-graphical) Reports from Project 2010 to Project 2013:
    I already put all these Reports in a transfer Project but they are no longer visible in Project 2013.
    The Customer is NOT willing to pay for the complete revision of the 50 Reports and rather gives up to pass to Project 2013 .
    What can I do?
    Monday, October 14, 2013 9:07 AM

All replies

  • Hi Ambrogio,

    Alas this is not possible - the old reports in Project 2010 and prior (with the exception of Visual Reports) are not available in Project 2013.


    Ben Howard [MVP] blog | web

    Monday, October 14, 2013 10:35 AM