Summary View with Milestone Markers RRS feed

  • Question

  • Hello,

    Is it possible to create a summary view in Project that also includes milestone markers along the timeline?

    Would look something like this:

    Summary Task Name  | Start Date | End Date | [_____*______*____*______]

    (I will add an image as soon as I can).

    Thanks,

    Will

    Tuesday, February 14, 2017 3:54 PM

Answers

  • Will,

    Okay, then add the Rollup field to your Chart view, apply the Milestones filter, and set the Rollup field to "yes". You can also set the Rollup field in the Task Information window under the General tab on a task by task basis.

    Hope this helps.

    John

    • Marked as answer by Will Kelly Tuesday, February 14, 2017 5:30 PM
    Tuesday, February 14, 2017 5:28 PM

All replies

  • Will,

    The answer is probably "yes", but do you mean this

    or this?

    Or perhaps something else.

    John

    Tuesday, February 14, 2017 4:16 PM
  • Hi,

    The second option, in the GANTT view.

    Thanks,

    Will

    Tuesday, February 14, 2017 4:55 PM
  • Will,

    Okay, then add the Rollup field to your Chart view, apply the Milestones filter, and set the Rollup field to "yes". You can also set the Rollup field in the Task Information window under the General tab on a task by task basis.

    Hope this helps.

    John

    • Marked as answer by Will Kelly Tuesday, February 14, 2017 5:30 PM
    Tuesday, February 14, 2017 5:28 PM
  • Thanks John, 

    I was successful in getting the view created.

    Thank you,

    Will

    Tuesday, February 14, 2017 5:31 PM
  • Will,

    You're welcome and thanks for the feedback.

    John

    Tuesday, February 14, 2017 6:18 PM