  • We have a scenario where a surroagte timsheet was submitted to a manager who was on vacation. The resource for whom the surrogate was submitted was also on vacation. Now we wanted to recall the timesheet and submit to a different approver. Is that possible?

    Can the Time Tracking Admistrator do anything  ?

    Friday, September 17, 2010 6:02 PM

Answers

  • Hi Prity,

    Depends on what version you are using.

    For Project Server 2007, Dale is right: only the timesheet resource can recall the timesheet.

    For Project Server 2010, you can setup delegations which allow you to logon as the resource to recall the timesheet.