Custom fields in timesheet for every day.

Question
-
I need that staff fill timesheet every day and except spent time, specify a city from which they work and wrote in the comments that it was done.
Also, I need that managers can view the records of each employee.
How can I do?Friday, August 17, 2012 11:33 AM
Answers
-
Hi Alex_rg,
Please see Christophe's blog:
http://blogs.msdn.com/b/chrisfie/archive/2010/04/06/project-server-2010-timesheet-custom-fields.aspxSimilar thread:
http://social.technet.microsoft.com/Forums/en-US/projserv2010setup/thread/26c41c69-2179-482f-8333-f8500cc7a6b9/Hope that helps.
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
- Edited by Amit Khare - Project Management Consultant Friday, August 17, 2012 11:41 AM
- Marked as answer by dcc_1 Friday, August 17, 2012 2:00 PM
Friday, August 17, 2012 11:41 AM
All replies
-
Hi Alex_rg,
Please see Christophe's blog:
http://blogs.msdn.com/b/chrisfie/archive/2010/04/06/project-server-2010-timesheet-custom-fields.aspxSimilar thread:
http://social.technet.microsoft.com/Forums/en-US/projserv2010setup/thread/26c41c69-2179-482f-8333-f8500cc7a6b9/Hope that helps.
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
- Edited by Amit Khare - Project Management Consultant Friday, August 17, 2012 11:41 AM
- Marked as answer by dcc_1 Friday, August 17, 2012 2:00 PM
Friday, August 17, 2012 11:41 AM -
But in the timesheet I have only one field for each custom column. I have report period - one week.
So users should fill the timesheet each day? Because they can't fill custom columns for all days in report period.
Friday, August 17, 2012 2:13 PM -
Maybe anyone faced a similar problem.
Requires that users of his schedule to fill custom fields - the city from which to work that day. And the detail wrote in a note that was made.
Custom field in the Schedule added. But the problem lies elsewhere.
Let's say I have the reporting period - a week. Users can fill out a schedule each day and a few days once. But now, with the period equal to the week, in the schedule users have only one box for comments and one for custom column. Can I make these columns comments and custom column for each day. I think it can if to do the reporting period in one day, but then the users will not be comfortable to fill all week.
Is there a solution?Tuesday, August 21, 2012 7:34 AM