How to use PSI to change the resource of task RRS feed

  • Question

  • Hello , everyone!

    In pwa,I want to use PSI to change the resource of task,could you show me how to do it?

    Thursday, December 6, 2012 8:31 AM

Answers

  • Hi there--

    Please see PSI limitations:
    WHAT PSI doesn't do:

    • Changing the resource on an assignment. However, you can use the PSI to delete the assignment and create a new one.

    • Deleting or replacing a resource that has actual work accepted (actuals).

    If you don't have the ActualWork on the task assignment, Please use the ProjectWebservice & get the Assignment table from projectdataset & delete the AssignmentRow as per the the RES_UID /TASK_UID.

    Now, You create a new Assignmnet row for the new RES_UID for the TASK_UID in AssignmentRow.
    http://msdn.microsoft.com/en-us/library/office/websvcstatusing_di_pj14mref(v=office.14).aspx

    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by oulei2008 Thursday, December 13, 2012 9:16 AM
    Monday, December 10, 2012 9:12 AM