remove exception days from calendar RRS feed

  • Question

  • Because we have incorrectly set the administrative tasks as "Non-Working", many resources' working days have been changed to "Exceptions" days, can we reset all the those days to normal working days via configuration or with coding?

    Thanks.


    Kevin Li

    Monday, February 9, 2015 3:50 PM

All replies

  • A simple but tedious solution would be to switch the administrative line to "working time" and ask the users to recall and submit again their timesheets.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, February 9, 2015 4:05 PM
    Moderator
  • Hi Kevin,

    The exceptions should be added to the resource's calendar. You can try to edit the resources and update their calendars in MS Project

    Hope this helps

    Paul

    Monday, February 9, 2015 4:11 PM
  • KevinLi,

    By "coding" I assume you mean a macro (VBA) or if you're in a Project Server environment, perhaps PSI. And, yes, you can "fix" the problem with some VBA. I can't speak to PSI since I don't do Server. However, it really depends on how many instances you need to fix. If it's a limited number, then the manual approach may be quicker and easier than an automated approach.

    John

    Monday, February 9, 2015 4:11 PM