Unable to open the project. The workflow associated with the project has been terminated unexpectedly RRS feed

  • Question

  • Sometimes when I open my demand I get this error - ‘Unable to open the project. The workflow associated with the project has been terminated unexpectedly. Please contact your administrator.’

    Actually I’ve been working on EPM for one year and I’ve been through this error many times. Before I used to think that this is the problem of my custom-workflow. But this time I’ve been getting this error on the new site where I’ve been using Sample Proposal Workflow for all my demands.


    Dinesh Bhardwaj

    Wednesday, October 10, 2012 3:55 AM

Answers

  • Hi Dinesh--

    Please check the ULS logs for more details. So does this work when you change or restart the workflow?
    http://technet.microsoft.com/en-us/library/gg188108.aspx

    What is the service pack /CU level on project server 2010? Just a guess, Do you get the error when the workflow is completed successfully & you open it from PWA? If yes, You may need to validate the Dec 2011 CU:
    http://support.microsoft.com/kb/2596997

    Assume that a workflow for a project is successfully completed. When you try to open the project by using PWA after 60 days, you receive the following error message:
    Unable to open the project. The workflow associated with the project has been terminated unexpectedly.


    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by SunnyBhardwaj Wednesday, October 10, 2012 8:33 PM
    Wednesday, October 10, 2012 4:54 AM

All replies

  • Hi Dinesh--

    Please check the ULS logs for more details. So does this work when you change or restart the workflow?
    http://technet.microsoft.com/en-us/library/gg188108.aspx

    What is the service pack /CU level on project server 2010? Just a guess, Do you get the error when the workflow is completed successfully & you open it from PWA? If yes, You may need to validate the Dec 2011 CU:
    http://support.microsoft.com/kb/2596997

    Assume that a workflow for a project is successfully completed. When you try to open the project by using PWA after 60 days, you receive the following error message:
    Unable to open the project. The workflow associated with the project has been terminated unexpectedly.


    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by SunnyBhardwaj Wednesday, October 10, 2012 8:33 PM
    Wednesday, October 10, 2012 4:54 AM
  • Hi Amit,

    Thank you. 'Change or restart the workflow' thing worked.


    Dinesh Bhardwaj

    Wednesday, October 10, 2012 8:34 PM
  • yes Amit..that worked..thank you..!!

    but what could be the reason that this is happening??



    Dinesh Bhardwaj

    Friday, October 26, 2012 9:37 AM