Add a Task into WBS using PSI RRS feed

  • Question

  • I am able to add task in WBS using PSI. But task gets added in manual mode. How do I set it Auto mode while adding task? Which property of PSI needed to amke it Auto schedule mode in order to be seen in timesheet. Please advice
    Thursday, January 13, 2011 10:20 PM

All replies

  • Hi Ak_123,

    i check in 2010 SDK and i find TASK_IS_MANUAL property for the task entity: Gets or sets the Boolean value that specifies whether the task is scheduled manually or automatically. True if manually scheduled.

    Can be this related to your question?

    I hope this help you

    Best Regards

    Paolo O.

    • Proposed as answer by Paolo Olocco Friday, January 28, 2011 8:01 PM
    Tuesday, January 25, 2011 10:51 PM
  • Thanks Paolo,

    this was the property I was looking for. It worked for me...thanks again

    Now I can add task thru PSI and it gets added in auto mode if I set property false.

     

    appreciate your response

    arati