Custom Task Field not showing in PWA Resource Assignments page RRS feed

  • Question

  • I created a task custom field that allows the PM to communicate what resource is needed for each task...

    Then I create a custom view in the resource assignments that has said field... 

    When on PWA the tile of my custom field displays fine, but there is not data...

    What am I doing wrong?

    Friday, March 28, 2014 8:03 PM

All replies

  • Hi Angela,

    Maybe it is a silly question, but since you are usingProject Server,  why dont you simply use the native resource field? It will allow assigning enterprise resources with metadata and also timesheet and task update features.  Not doing this, you really cut yourself from the powerful features of Project Server.

    Then to answer your question, you have to ensure that the task field in question has values in the project and that the project has been correctly published.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS


    Saturday, March 29, 2014 8:55 AM
    Moderator