Task Effort shows as Hours and Man Days RRS feed

  • Question

  • Hi

    I hope someone can help

    I currently resource my projects with work set as hours, however I have been tasked with converting this figure into Man Days as an integer so we can determine how many contractors would be needed to be hired.

    I still want to work and report in hours in my plans, is there a way to add a column (enterprise preferably) which will calculate and show the Man Days each task takes in my plans?

    Thanks in advance

    Matt 

    Wednesday, November 22, 2017 9:24 AM

Answers

  • Matt22365,

    It becomes pretty straightforward with a custom field formula that looks something like this:

    Text1=[Work]/[Minutes Per Day] & " mdays"

    Hope this helps.

    John

    • Marked as answer by Matt22365 Thursday, November 23, 2017 8:47 AM
    Wednesday, November 22, 2017 2:44 PM

All replies

  • Matt22365,

    It becomes pretty straightforward with a custom field formula that looks something like this:

    Text1=[Work]/[Minutes Per Day] & " mdays"

    Hope this helps.

    John

    • Marked as answer by Matt22365 Thursday, November 23, 2017 8:47 AM
    Wednesday, November 22, 2017 2:44 PM
  • Hi

    Fantastic, thank you John.

    Matt

    Thursday, November 23, 2017 8:47 AM
  • Matt,

    You're welcome and thanks for the feedback.

    John

    Thursday, November 23, 2017 3:58 PM