Making formulas recognise the calendar when working out dates RRS feed

  • Question

  • Hi

    I am using the following formula in the Date1 field "[Early Start]+([Free Slack]/480)" (in MSP 2007 Professional). The problem is that it does not take into account weekends or holidays. Could someone advise how I can reference the project calendar in this formula.

     

    Many thanks

     

    Andrew

     

    Friday, March 11, 2011 2:08 PM