Creating a .mpp from .xlsm, how do I turn off manual scheduling for the app and tasks RRS feed

  • Question

  • I must admit, this is one of the "improvements" I dislike most about project 2010.  Why give PMs the ability to turn project into an excel spreadsheet, something which they would want to be using anyways lol.

    Anyways, rant over.

    I am creating a .mpp from an excel extract and when I build the schedule, every activity and the app stays in manual schedule mode which means my gantt bars all take the default manual scheduled look and feel.

    Is there any way on the build to change this to autoscheduled mode?

    Thanks

    Sean