  • Hello,

    I have a custom code activity which is being used in multiple workflows. Now say I have a bug, I need to implement a newer version of the code activity.

    Whats the best approach to do it. Stopping all workflow managers doesnt suits me as there are other workflows which are not using this code activity.

    regards

    Monday, February 18, 2013 8:57 PM

All replies

  • Unfortunately, with custom code activities, you need to stop the Workflow Manager Backend Service, deploy your assembly with the newer version and then re-start the Workflow Manager Backend service. If you have a HA configuration for your Workflow Manager farm, you might be able to overcome this hiccup by re-starting this service one node at a time.
    • Proposed as answer by DevKC Thursday, February 21, 2013 3:34 AM