What is the difference between Timesheet Manager & Status manager? RRS feed

  • Question

  • What is the difference between Timesheet Manager & Status manager?


    What is the main difference between Timesheet & Task?
    • Edited by MSP-Learner Wednesday, July 11, 2012 8:31 AM
    Wednesday, July 11, 2012 8:28 AM

Answers

  • The timesheet manager is the person who approves the resource's timesheet. The Status manager is the person who approves the task status in the Project plan. The status manager is typically the project manager or project owner, however the system supports multiple status managers on a single project.

    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG

    Wednesday, July 11, 2012 8:43 AM
  • Hi Ankit,

    Project Server has feature of  tracking progress for the projects & tracking billable and nonbillable hours. Based on organization needs, We can have one or both options enabled in system.
    Status Manager is responsible to approve/reject task updates from Team members & Timesheet manager is for approving  the timesheets.  Please see below article which explains in details: http://office.microsoft.com/en-us/project-server-help/overview-of-timesheets-and-task-status-HA010146635.aspx

    Timesheet is the sanpshot of tasks taken while cretaing & doesn't update the actual hours in project plan unless you have SEM enabled. My tasks updates are applied to project progress.

    If you are loooking at the PS2007, Please see Marc's blog:http://marcsoester.blogspot.in/2008/03/project-server-2007-timesheets-goods.html

    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by MSP-Learner Wednesday, July 11, 2012 9:37 AM
    Wednesday, July 11, 2012 8:48 AM

All replies

  • The timesheet manager is the person who approves the resource's timesheet. The Status manager is the person who approves the task status in the Project plan. The status manager is typically the project manager or project owner, however the system supports multiple status managers on a single project.

    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG

    Wednesday, July 11, 2012 8:43 AM
  • Hi Ankit,

    Project Server has feature of  tracking progress for the projects & tracking billable and nonbillable hours. Based on organization needs, We can have one or both options enabled in system.
    Status Manager is responsible to approve/reject task updates from Team members & Timesheet manager is for approving  the timesheets.  Please see below article which explains in details: http://office.microsoft.com/en-us/project-server-help/overview-of-timesheets-and-task-status-HA010146635.aspx

    Timesheet is the sanpshot of tasks taken while cretaing & doesn't update the actual hours in project plan unless you have SEM enabled. My tasks updates are applied to project progress.

    If you are loooking at the PS2007, Please see Marc's blog:http://marcsoester.blogspot.in/2008/03/project-server-2007-timesheets-goods.html

    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked as answer by MSP-Learner Wednesday, July 11, 2012 9:37 AM