none
Find the summary level RRS feed

  • Question

  • With a task from the ActiveSelection.Tasks collection, I'd like to find the summary level and retrieve its attributes.  What is the quickest way of doing that?

    Thanks for your advise in advance.

    Friday, August 5, 2011 4:23 PM

Answers

  • Hi,

    I suppose you mean the summary task?

    Activeselection.tasks(1).outlineparent 'this yields a task

    The outline level is found as

    Activeselection.tasks(1).outlinelevel

    Greetings,

    • Marked as answer by ATorng Saturday, August 6, 2011 4:31 AM
    Friday, August 5, 2011 5:47 PM
    Moderator

All replies

  • Hi,

    I suppose you mean the summary task?

    Activeselection.tasks(1).outlineparent 'this yields a task

    The outline level is found as

    Activeselection.tasks(1).outlinelevel

    Greetings,

    • Marked as answer by ATorng Saturday, August 6, 2011 4:31 AM
    Friday, August 5, 2011 5:47 PM
    Moderator
  • Hi, Jan -

    Wow!  Works like a charm.  Really appreciate your help.

    Andre


    AndreT from MS Project Customization and Programming Forum
    Friday, August 5, 2011 8:20 PM