none
Task ratings - is it possible? RRS feed

  • Question

  • Hi,

    There is a need to have ratings (0.8 - bad, 1 - good, 1.2 -excellent) next to each task and to calculate average rating for every month and every user with multiple published projects. Would it be possible at all? 

    Monday, July 2, 2018 6:22 AM

Answers

  • Hi,

    You could always create a task custom field and roll it down to assignment level. But it won't be timephased and recorded every month by default to keep the history. Thus you'll need to develop a custom development to store the data.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by TRIUMF Monday, July 2, 2018 8:23 AM
    Monday, July 2, 2018 7:40 AM
    Moderator

All replies

  • Hi,

    You could always create a task custom field and roll it down to assignment level. But it won't be timephased and recorded every month by default to keep the history. Thus you'll need to develop a custom development to store the data.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by TRIUMF Monday, July 2, 2018 8:23 AM
    Monday, July 2, 2018 7:40 AM
    Moderator
  • Thanks! I tried to play with custom fields, but it seems tricky to collect that data from all projects and make a report. At least now I know that such scenario is not built-in.
    Monday, July 2, 2018 8:23 AM