Creating a days worked report at the beginning of each month. RRS feed

  • Question

  • I am looking to create a report at the beginning of each month to project how many "man days" are projected to be worked each month. The closest I have got is by modifying the milestone report already set up but I still can't get a result.

    I've also tried using the resource graph but short of counting up each day for each engineer there doesn't seem to be a simple sum function available that can be customised for a calendar month.

    Thanks for your help.

    Wednesday, February 3, 2016 9:07 AM

Answers

  • Hi,

    You could use the resource sheet and resource graph cumulating all resources.

    You can follow this procedure: http://blogs.catapultsystems.com/alavinsky/archive/2009/06/16/project-pro-leveraging-the-resource-graph/

    Then in the format tab, choose "month" for the timescale.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by steve183 Wednesday, February 3, 2016 10:23 AM