MSP 2013 is Microsoft Project 2013. Is it right?
SharePoint does not directly support the different predecessor types (e.g. Finish-to-Finish, Start-to-Start) and task dependencies, such as Lead and Lag times, any impact on dates (Start, Finish etc.) are fully reflected in SharePoint.
More information, please refer to the link:
http://www.manageprojectsonsharepoint.com/blog/2013/05/13/the-improved-sharepoint-2013-to-project-sync/
http://blogs.technet.com/b/projectsupport/p/ps13cu.aspx
As this issur is about Project, I suggest you create a new thread on Project forum. The reason why we recommend posting appropriately is you will get the most qualified pool of respondents, and other partners who read the forums regularly can either share
their knowledge or learn from your interaction with us. Thank you for your understanding.
Project forum:
https://social.technet.microsoft.com/Forums/projectserver/en-US/home?category=project
Thanks,
Wendy
TechNet Community Support
Please remember to mark the replies as answers if they help, and unmark the answers if they provide no help. If you have feedback for TechNet Support, contact