Finding linked fields in Microsoft Project RRS feed

  • Question

  • You can link date fields in an MSP task using Paste Special.  This is detectable programatically using VSTO by the boolean LinkedFields on the task.  But is there a way to find out what these links are?  (I am interested in links just between tasks in the same project, not to other files.)   
    Thursday, September 3, 2015 3:35 PM

All replies

  • Hello Tony,

    VSTO doesn't provide anything for that. I'd suggest asking Project specific programming questions on the General Office Development  forum instead.

    • Proposed as answer by David_JunFeng Monday, September 21, 2015 9:46 AM
    Friday, September 4, 2015 7:59 AM
  • Hi Tony,

    This forum is used to discuss and ask questions about using Visual Studio to create managed code solutions for Microsoft Office, your issue is related with Project developing, I will move this thread to the more related forum.

    Reference: http://social.msdn.microsoft.com/Forums/en-US/home?forum=project2010custprog

    Thanks for your understanding.

    Best Regards,

    Edward