  • Question

  • I would like to incorporate not only my ME department, but also the ME department in Hungary. Now there are 4 other engineers there so I want to label a resource "Hungary" and then use 160 hrs/wk specifically for them. No matter what options I look through on the resource page, there is no way for me to individually adjust the amount of time each resource can spend during the week. Thanks for the help.