A lot of custom fields RRS feed

  • Question

  • Hello

    In one of our environment, we currently have 70 custom fields as follow (onely one is calculated).

    Formula

    Entity

    Type

    Count of Last Updated

    No

    Project

    Cost

    7

    Date

    5

    Number

    3

    Text

    40

    Resource

    Text

    5

    Task

    Cost

    5

    Flag

    2

    Text

    2

    Yes

    Task

    Cost

    1

    Grand Total

    70

    we would like to evaluate the impact on adding 20 more project custom fields 

    14 of those fields will be supported by one Lookup Table and the 6 others will be free text.

    Do you see any drawbacks in adding such number of CF?


    Wednesday, May 29, 2013 9:14 PM

Answers

  • jejetator,

    I don't quite understand your diagram of fields, a screen shot would have been much better. But, understanding the details isn't really the crux of your question.

    Generally speaking, more customization leads to larger files. On the good side, you don't appear to have tons of complex formulas and if you only have one or two lookup tables it shouldn't be too bad. It looks like most of your custom fields are strictly for pieces of "simple" data.

    That's my two cents.

    John

    Wednesday, May 29, 2013 10:42 PM

All replies

  • jejetator,

    I don't quite understand your diagram of fields, a screen shot would have been much better. But, understanding the details isn't really the crux of your question.

    Generally speaking, more customization leads to larger files. On the good side, you don't appear to have tons of complex formulas and if you only have one or two lookup tables it shouldn't be too bad. It looks like most of your custom fields are strictly for pieces of "simple" data.

    That's my two cents.

    John

    Wednesday, May 29, 2013 10:42 PM
  • Hello John

    thanks for your reply.

    the pivot table past did not work as expected.

    should be more understundable like that

    Formula Entity Type Count  Count of Lookup Table
    No Project Cost 7
    No Project Date 5
    No Project Number 3
    No Project Text 40 26
    No Resource Text 5 5
    No Task Cost 5
    No Task Flag 2
    No Task Text 2 1
    Yes Task Cost 1
    Grand Total 70 32

    in what you say I may concider that it's no big deal adding more fields while it's not calculated ones.

    thanks

    Jérome



    Jérome

    Thursday, May 30, 2013 12:38 PM