Tanbirul_islam --
The project managers can see all of the resource assignment information using the Resource Usage view in the Microsoft Project schedule. To see the resource assignments on all projects, a project manager should do the following in Project Web App:
- Navigate to the Resource Center page and select the checkboxes for the resources of interest.
- In the Resources ribbon, click the Resource Assignments button.
To see all resource assignments in all projects for all resources would require a custom report. Hope this helps.
Dale A. Howard [MVP]