You need to understand how Project works, so manually do what you think you need by editing the duration field directly, editing work or resource units.
Then record a macro of you doing what you want to get the relevant VBA code. Unless the task is happening now, use any method that does not set a task constraint. Task constraint change the critical path, require manual updating and cost you time and effort.
Happy programming
Rod Gill
Author of the one and only