I would check the Project calendar first --> Click on Project tab in project professional the menu and click on "Project Information", check the calendar.
Otherwise, open the task, click on Advanced, check the calendar attached to that task.
Later, go to resource sheet, open the resource, click on change working time to check the resource calendar.
Ensure you have appropriate calendar using "change working time" in Project tab to identify the calculation.
Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management