  • Question

  • We have started a content deployment task that is stack and runing for more than a week, I tried to stop it but was not able to find any way to stop or cancel.

     

    Any body have any Idea, Please help


    Best Regards, Syed Muhammad Ehsan MCTS SharePoint Server 2007 (Dev & Config)
    Sunday, July 31, 2011 8:34 AM

Answers

  • Hi,

    Login to central admin--> Operation-->Content Deployment Paths and Jobs.

    Here you will find your job enlisted out. You can stop that from here.

     