Project Metrics RRS feed

  • Question

  • There are a set of metrics for define if plan is LOE, is good or bad and so?

    For example, I have 300 plans, and I want a objectiv metric (extract from Project DB) for plans calssification

    Thanks for your opinions

    Sunday, May 14, 2017 4:33 PM

All replies

  • Not going to work I'm afraid. The success criteria for each project is very likely to be quite different so success monitoring for each project usually has to be different. EG compare a tight timeframe project with a must deliver 50% better productivity project. Time is critical for the first but probably not for the second.

    If all projects are similar, eg 300 painting projects, then there is cost variance and finish variance etc.


    Rod Gill
    Author of the one and only Project VBA Book and VBA developer.
    www.project-systems.co.nz

    Wednesday, May 17, 2017 9:45 AM