calculate and rollup %complete of each resource RRS feed

  • Question

  • Looking for automated way to calculate and rollup %complete of each programming resource. For example, Project would calculate all of the assigned tasks (whether the tasks were complete 100% or not), add up all of these programmers tasks and divide by the total. Right now I do this by hand but looking for an automated report from Project 2010.

    Thanks in advance.

    Tuesday, September 4, 2012 1:39 PM

All replies

  • Hello Rick,

    I may have misunderstood your requirement, but have you looked at the column labelled "% Work Complete" in the Resource Sheet view? It would appear to do what you've described natively.

    Thanks,
    Andrew

    • Proposed as answer by Andrew Simpson Thursday, October 11, 2012 3:17 PM
    Tuesday, September 4, 2012 2:16 PM