Mark a iterationas released? RRS feed

  • Question

  • How do I mark a iteration as released? We have completed the work in the iteration, and I would like the next iteration as the current one.
    Wednesday, May 7, 2014 2:41 PM

Answers

  • Hi Jagdip,

    To get into the next iteration, you can edit the end date of current sprint to a passed date. Then refresh the web page, the current sprint will be changed.

    Best regards,


    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click HERE to participate the survey.

    • Marked as answer by Jagdip Thursday, May 8, 2014 8:20 AM
    Thursday, May 8, 2014 2:01 AM