Unique ID of a summary task RRS feed

  • Question

  • How do I find the Unique ID of the summary task header.
    For Example:
    Task 1       UID 1
       Task 1_1  UID 2
       Task 1_2  UID 3
    Task2        UID 4
       Task 2_1  UID 5
       Task 2_2  UID 6

    So if I am on Task 2_2 for example, the unique ID of its summary record would be 4.

    I can find predecessor and successor ID but not the ID of the summary task for any task.

    Cheers
    David

    Tuesday, August 2, 2011 11:34 PM

All replies

  • David,

    Since you are posting to the customization and programming forum I'll assume you are trying to find the data programatically. The following line of VBA code will provide the unique ID of the parent task (i.e. summary line) for working task 2_2

    UID=activeproject.Tasks(6).OutlineParent.UniqueID

    Hope this helps.

    John