Can You Change Resource Bill Rate for a Project in Project Server 2010? RRS feed

  • Question

  • Hello All,

    I know we can set a Standard Rate (and OT Rate) for each Resource in Server Settings > Security > Manage Users.  Can we vary that Rate, by Project.  For example, if Resources are normally billed at $150/hour, but on a particular project we negotiated $140/hour for Developers and $160/hour for Consultants.  Is there a way to modify billing rates, by Resource, by Project?  

    I don't want to change the Resource's User record because the Standard Rate still holds true for other active projects on which that Resource(s) works.  Thank you!

    Julie