none
Marking MTM Test Step Result as Blocked - Only Pass and Fail are Available Options RRS feed

  • Question

  • Hello,

    We're using MTM 2013 for all our project test requirements. When we manually run our Test Cases, each test step result can currently only be marked as Pass or Fail. There is however a requirement for us to supply an additional value "Blocked", so individual test steps can be marked as such during a manual test run.

    Is it possible to achieve this in MTM at all?

    Thank you.

    Wednesday, September 16, 2015 3:56 PM

Answers

  • Hi,

    We can’t set the test step result to Blocked.

    For this scenario, you could set the test result status to Blocked. (click Mark test case result icon and select Blocked)

    If you still want that feature of mark test step Blocked, I suggest that you could submit this feature request: http://visualstudio.uservoice.com/forums/121579-visual-studio. The Visual Studio product team is listening to user voice there. You can send your idea there so the others can vote it. If you submit this suggestion, you might post that link here which will benefit others who has the similar issue.

    Regards

    Starain


    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click HERE to participate the survey.

    Thursday, September 17, 2015 7:49 AM