none
MS Project Negative Lag Not Calculating Correctly RRS feed

  • Question

  • Negative lag entered on a task as;

    Task Id and name, FS-10d

    Task is due on the 18th so negative date for ordering should be shown as the 8th. However, task is showing as a date of the 18th. Positive lag is calculating correctly.

    Wednesday, October 2, 2019 9:13 AM