    I'm trying to create project by importing data from xml-file. Almost everything is working fine, I get required resources and tasks? but when I click on task information - ok , all my tasks start dates are changed.

    I guess, the question is not pretty clear, so I made a video for better understanding youtu.be/ey_3VHj5lck

    Monday, March 11, 2019 1:49 PM

All replies

  • Hi,

    You first have to check if you import correctly the start date. Check the date format. Also do you use the predecessor information? The last thing to check is the task type (manual or automatic). If your MS Project is configured with manually scheduled tasks by default, the task will be imported in manual mode from the XML and most of the calculation rules of the scheduling engine will be deactivated.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, March 11, 2019 2:21 PM