Wrong Days Calculation RRS feed

  • Question

  • 

    I've put in the settings that I work 7 days a week, now when I add tasks it calculate the days wrong.

    7 + 3 Days should be 10 Days and not 7 Days.

    Why does it happen ?


    • Edited by Aviv0099 Sunday, February 12, 2017 7:13 AM
    Sunday, February 12, 2017 7:13 AM

All replies

  • Hi,

    First thing is to set tasks to auto scheduled mode. The tasks 2 and 3 are manually scheduled which deactivates some of the scheduling engine calculations. Then ensure that the tasks 2 and 3 are linked (if you want them to be subsequent).. The summary task duration takes the duration between the earliest start date of children tasks and the latest finish date. 


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Sunday, February 12, 2017 12:45 PM