locked
Resource Assignments in MS Project 2007 RRS feed

  • Question

  • Hi,

    I am working on Project Server 2007. Is it possible to view the enterprise resource assignments in all projects in MS Project?

    I know that it is possible to view in PWA through Resource Center but let me know is that possible to view in MS Project 2007.

    Regards

    K.Gokulraj

     

    Wednesday, February 16, 2011 10:41 AM

Answers

  • K.Gokulraj --

    Using Microsoft Project 2007, the only way to view the resource assignments in all projects is to open EVERY project and then apply the Resource Usage view.  This will show you every task assignment for every resource.  A better approach might be for your Project Server administrator to create a Data Analysis view for this purpose.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, February 16, 2011 1:17 PM

All replies

  • Hi,

    You can view the project the resource is currently working in from Project Professional 2007. but that in a case when you try to use the resource in a project. Click the View menu and change the view to Resource usage, it will show all the details of the enterprise resource.

    Also have you tried to use the Project Professional visual reports, there are few Resource Assignment reports might fulfill you requirement.

    Does this help.

     


    | Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |
    Wednesday, February 16, 2011 10:58 AM
  • Khurram,

    Thanks for your reply.

    My question is, consider i am the Portfolio Manager. i want to see the global resource pool in MS Project 2007.

    I want to see all enterprise resources details such as who is working on what, when. who is over allocated, when he is over allocated etc.

    Please let me know how to view these information related to all enterprise resources in MS Project 2007.

    Regards

    K.Gokulraj

     

    Wednesday, February 16, 2011 1:16 PM
  • K.Gokulraj --

    Using Microsoft Project 2007, the only way to view the resource assignments in all projects is to open EVERY project and then apply the Resource Usage view.  This will show you every task assignment for every resource.  A better approach might be for your Project Server administrator to create a Data Analysis view for this purpose.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"