Custom Timephased cost fields in Project Server 2010 RRS feed

  • Question

  • Hi,

    Is there a way to split out over time custom made task cost fields ?

    I have a task cost field depending on a lookup table.
    for instance
    A -- $100
    B -- $200
    C -- $300

    Now depending on where my task is located i had to multiply this by a factor to calculate the correct cost.
    Level 1 multiply by 2
    Level 2 multiply by 2.5
    level 3 multiply by 3

    Now i can calculate the cost of a specific task by multiplying the selected value of my lookup table by the factor.
    Now i can see the cost for this field.

    But is there a view available that added this cost to the total task cost.
    Even i need to see, what's the daily cost of my task.
    so can i make this cost timephased, so i can easily put this in a cube, or another report.
    To split out my custom field during the total task time ?

    Thx

    Tom

    Wednesday, April 11, 2012 9:38 AM