Sample proposal workflow stays in Proposal Selection RRS feed

  • Question

  • Hi Guys,

    I've been trying to figure out how Sample Proposal Workflow works. I've one user with Portfolio rights and one with PM. PM starts a wf and it goes fine and Portfolio guys receives notification for all approvals and reviews, but this stops at Proposal Selection stage. I don't know to whom the request is sent to. I don't find any documentation regarding this. There's link i found on net of video walk through but that doesn't work. Please help!

    Thanks,

    Kashif


    Thanks, Kashif

    Sunday, September 9, 2012 6:03 PM

Answers

All replies

  • Hi Kashif--

    I was working on a recent case for a customer & came up with the same question. 
    Once the proposal is done with selection review under create phase, It's ready for the Proposal selection using Portfolio analysis. As per the analysis, System doesn't send email/notification to Portfolio manager/group that proposal is ready for the selection process.

    Scenarios for Project Server Development: 
    http://msdn.microsoft.com/en-us/library/office/ee767682.aspx

    I am sure that you know you can create a send email step in workflow for notification. 

    I'll allow others to correct me  if I am wrong.

    Thanks,


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Monday, September 10, 2012 5:24 AM
  • Hi Amit,

    Thanks for the reply. As far as the notification is concern it's fine at this moment. I was unable to proceed from Proposal Selection. After posting this, I found out that it has to be Committed via Portfolio Analysis to proceed. Now, I've moved to Resource Planning stage, where I am stuck again how to move forward from here. I was just wondering if there is any proper site which can guide me for running the whole WF cycle.

    Thanks


    Thanks, Kashif

    Monday, September 10, 2012 6:13 AM
  • Hi Kashif--

    Ok, In that case, looks like that you need to check your Portfolio analysis 
    Please make sure that you created a resource plan in proposal  & checked "Analyze time-phased project resource requirements against organizational resource capacity " during Portfolio analysis  & once you select it, the plan phase that have the Resource planning will be analyzed & commit. Once you commit that this will move from Resource planning to Scheduling.

    Please see below thread:
    http://social.technet.microsoft.com/Forums/en-US/projserv2010setup/thread/c95753bf-c257-42b7-8149-dfea7146ee17

    HTH


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82


    Monday, September 10, 2012 6:54 AM
  • Andrew's whitepaper is having all step by step. Might be useful for you.
    http://technet.microsoft.com/en-us/library/gg715564.aspx


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82


    Monday, September 10, 2012 7:02 AM
  • Thanks a lot Amit! You are the man! :)

    I was exactly looking for that. Thanks again!


    Thanks, Kashif

    Monday, September 10, 2012 8:45 AM
  • You are more than welcome :) Kashif.  Glad that I was able to help.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82