none
can we filter out the fourth level tasks based on the level 1 and Level 2 tasks in project server 2010? RRS feed

  • Question

  • Hi
    I have four levels of Task in the project Plan.I have to create report on fourth level task and need to do the the filtering of these tasks by selecting task Level 1 and Level2

    that is I need to select a value for Level2 Task, then fourth level subtasks of this selected level 2 task only be available in the report.

    Please help


    Thanks, Lovely

    Friday, May 4, 2012 2:00 PM

Answers

  • Hi there-- Hope the below thread helps. http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/2035bc16-0f64-415c-8451-980821f14b02 Thanks,

    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Friday, May 4, 2012 2:17 PM

All replies

  • Hi there-- Hope the below thread helps. http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/2035bc16-0f64-415c-8451-980821f14b02 Thanks,

    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Friday, May 4, 2012 2:17 PM
  • Thanks a lot Amit.

    The thread you have mentioned really helped and it worked for me :)


    Thanks, Lovely

    Monday, May 7, 2012 2:41 PM