Multiple dependencies in ADF V2?

    Question

  • Is it possible to have multiple dependencies for execution of a pipeline or activity?

    Currently, we have a 3 pipelines that run in parallel, and then another one that is supposed to run once all 3 are finished successfully. However, that last pipeline runs as soon as the first one finishes. Is there any way to make that last one wait until all the others are done?

    Friday, August 3, 2018 7:22 AM

All replies

  • Hi John, 

    Check out the document here: https://docs.microsoft.com/en-us/azure/data-factory/concepts-pipelines-activities#activity-dependency

    It mentions that one activity can depend on one or multiple of other activities. You can define multiple dependencies in the dependsOn property.

    Friday, August 3, 2018 7:28 AM
  • It turned out that the Wait for completion flag was not selected on one of the pipelines feeding into the final activity.  
    Friday, August 10, 2018 5:22 PM