none
Task Work Issue RRS feed

  • Question

  • Dear all , I am creating a new task through PSI, and and it is working fine. But the Value TASK_WORK is not changing in the PAS site taskRow.PROJ_UID = dsProject.Project[0].PROJ_UID; taskRow.TASK_UID = Guid.NewGuid(); taskRow.TASK_DUR_FMT = (int)PSLibrary.Task.DurationFormat.Day; taskRow.AddPosition = position; if (position == PSLibrary.Task.AddPosition.Middle) { taskRow.AddAfterTaskUID = predecessorGuid; } taskRow.TASK_NAME = taskName; taskRow.TASK_WORK = 50; dsProject.Task.AddTaskRow(taskRow); Please help me what could be the reason.
    Saturday, December 25, 2010 9:59 AM

Answers

  • I have got worked becuase Onece u assigne the TASK_WORK to task, u need to assign it  to the assignment record also.

     

    thnks

    saju

     

    • Marked as answer by SAJUKA Saturday, December 25, 2010 2:40 PM
    Saturday, December 25, 2010 2:39 PM