Test for Baseline Finish date set RRS feed

  • Question

  • Hi,

    I am trying to write a formula that tests that a Baseline Finish date exists.  So far, I cannot determine the appropriate value that represents NA (no baseline value set).

    I am running Project Online with Project Pro 16 on the desktop.

    Any help would be appreciated.

    Cathy

    Friday, July 7, 2017 2:15 AM

All replies

  • Hi,

    the formula is [Baseline Finish]=ProjDateValue("NA") if you are working in an English only environment. If you are in a multilanguage environment, ProjDateValue([Baseline Finish])=4294967295 is the better solution, since it is independent from langauge settings.

    Does that work?
    Barbara

    Friday, July 7, 2017 6:28 AM
    Moderator