none
VBA proc to update resource calendar (Project Server 2010) RRS feed

  • Question

  • Hello,

    I created a VBA procedure which reads an Excel Workbook generated by an external application where are entered the resources holidays. This macro fills in the resource calendars in a Project Standard 2010 .mpp file. It works fine : 50 resource calendars are updated within half a second.

    Now I need to adapt this VBA proc to do the same thing in Project Server 2010.

    How can I do that? In the Enterprise Global?

    Any advice ?

    Thanks for your help.



    • Edited by WLID1966 Sunday, July 7, 2013 1:28 PM
    Saturday, July 6, 2013 4:09 PM

Answers

  • Hi,

    Open the enterprise resource pool. Use your VBA therein. Then save the enterprise resoruce pool. Works - I did it a few years ago.

    • Marked as answer by WLID1966 Saturday, July 2, 2016 5:21 PM
    Sunday, July 7, 2013 7:02 PM
    Moderator