Global (default) Resource Rates in Project Online RRS feed

  • Question

  • Is there an easy way to setup a default resource rate in a Project Online resource pool?
    Monday, April 20, 2015 6:31 PM

Answers

  • Jim,

    No, using the GUI. Resource Rates are per resource, and will have to be populated when creating the resource.

    However, you can bulk edit the resources in project pro and set the standard rate in one go.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Monday, April 20, 2015 6:54 PM
    Moderator

All replies

  • Jim,

    No, using the GUI. Resource Rates are per resource, and will have to be populated when creating the resource.

    However, you can bulk edit the resources in project pro and set the standard rate in one go.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Monday, April 20, 2015 6:54 PM
    Moderator
  • THANKS!! That worked quite well actually.
    Monday, April 20, 2015 7:02 PM
  • Glad it worked. Please mark as answer, so that other can find it as well!