PSI - Calculate values ​​of custom fields RRS feed

  • Question

  • Hi, 

    (PS2007)

    We currently have a web service that automatically publishes all our projects, but in PWA custom field values ​​with the publication are not updated. 

    Is there any method or way to calculate the values ​​of the custom fields through web services so that they can be displayed in PWA. 

    regards,
    Monday, July 21, 2014 7:30 PM

All replies

  • Hi

    Are you updating these custom field values using PSI before publishing the projects ?

    Are you using formula's in custom field  ?, You may try publishing the projects using Project professional( use macro if you want to publish more projects) so that it uses the client scheduling engine.

    --Hope this helps


    Thanks --Ajith

    Wednesday, July 23, 2014 1:22 PM
    Moderator
  • Ajith,  Thanks for your reply

    Yes, the custom fields contain formulas. We are using methods such as (CheckOutProject, QueuePublish, QueueCheckInProject) with which we opened, publish and then close each project, but using what is stated above, it is not ensured that the values ​​of the formulas can be updated in PWA. You know any method to perform this action? (recalculate and update the values​​).

    Thanks in advance,


    Thursday, July 24, 2014 10:04 PM
  • Did you ever find an answer?

    Ian