Level of Effort in project server RRS feed

  • Question

  • Hi,

    We are trying to use LoE to define how many employees from each kind will be needed per each time-frame.

    Meaning for example:

    There are 3 different employees type (A,B,C). and we want to define that a specific Hammock (linked to start and end of specific tasks) requires for example 1.5 of employee A, 2 employees B and 4 employees C. AT each day of the Hammock duration.

    So, if the Hammock expend, the total work increases accordingly and vice versa.

    The problem is that we get an error massage each time we open MSP due to the links ("Project X contains linked information.."). and the linked data do not work properly. 

    Any idea or proposal fora different approach?

    Thanks,

    Eyal

    