Try to set TASK_PCT_COMP to 100 via PSI --> not working RRS feed

  • Question

  • Helllo everybody,

    I'am working with a Project Server 2010 and the PSI.

    At the moment I try to change the TASK_PCT_COMP of some tasks in some projects with the PSI.

    There I get the dataset, change the values and then update the Project.
    But then nothing happens. I tryed the same via ProjTool.

    The work (TASK_PCT_WORK_COMP) of these Tasks are 100. But the Task_REM_DUR >0 . When I try to change the Task_REM_DUR to the value of TASK_ACT_DUR I get the error "ProjectActualsAreProtected".

    In the Project Client this is no Problem.

    Can somebody help?

    Thanks in advance.

    Best regards,

    Marc

    Monday, June 3, 2013 2:26 PM