How to set Task % Complete in Microsoft Project xml? RRS feed

  • General discussion

  • I am trying to generate Microsoft Project XML. Everything seem to import correct in Project apart from % Complete on tasks. I have set task start, finish, early start, finish, late start finish, PercentComplete, duration, actual duration, remaining duration, TimephasedData for each day.

    I can see it is all exported correctly in XML however when I import into Microsoft Project, it changes % Complete. 

    I am using formula given on http://office.microsoft.com/en-gb/project-help/percent-complete-fields-HP001024590.aspx to calculate % Complete but it does not seem to work?

    Can anyone please tell me how does it calculate % Complete, % Work Complete, PhysicalPercentComplete please, or if you can provide me where I can read about each field in XML and how it is calculated or effects other fields while importing in MS Project it would be great help.

    Vinayak


    Vinayak Nirvani.

    Thursday, December 19, 2013 10:48 AM

All replies

  • http://www.mpug.com/articles/ask-the-experts-when-complete-wont-calculate/

    go with the link.

    Below mentioend link will give you idea about % complete, Physical % complete and % work complete

    http://ntrajkovski.wordpress.com/2013/10/30/complete-vs-physical-complete-in-ms-project-2013/


    kirtesh


    • Edited by Kirteshtiw Thursday, December 19, 2013 11:09 AM
    Thursday, December 19, 2013 11:00 AM
  • Hi Kirtesh,

    Thanks for your quick response. I read ntrajkovski blog about % Complete, % work complete & Physical Percent complete. I understood how they work but in my case I am generating XML manually and I am setting % Complete in my xml but when I import that xml into Microsoft Project. It changes % Complete to 0 or 100. So I am trying to understand the calculations it does while changing % Complete.


    Vinayak Nirvani.

    Thursday, December 19, 2013 11:38 AM
  • Have you gone through http://www.mpug.com/articles/ask-the-experts-when-complete-wont-calculate/

    And as you told you are setting up manually i am sure you are not setting it on task basis and doing it on Project or Summary task basis that is why when you import to Project professional value is getting changed.

    MS Project has Roll up means it calculate % complete in Task basis then summary task then project.

    I mean to say If you have summary task then 4 task under it then % complete of summary task will be based on all the four task and if project plan is having 5 summary task then % complete for entire project will be based on % complete of Summary Task.

    or if you have 3 task and all are 5% completed then Project % complete will be 5 if any one of the task is having 10 then project % complete will be (5+5+10)/3=6.66 means 7% it means it takes average.  

    Hope it helps.. 


    kirtesh


    • Edited by Kirteshtiw Thursday, December 19, 2013 12:02 PM
    Thursday, December 19, 2013 11:52 AM
  • Hi Kirtesh,

    I went through that link too. but that post is about setting task as complete. but I dont want to set it as complete. I am trying to generate xml that can be imported in Microsoft Project.

    I understand about summary tasks. But my question is regarding normal task which is not summary. All I am trying to do is add task which is 50% complete and has 1 resource assigned to it.


    Vinayak Nirvani.

    Thursday, December 19, 2013 1:56 PM
  • When you are creating task you have to add following in XML file for adding a task 

    <Task>

                                                    <UID>1</UID>

                                                    <ID>1</ID>

                                                    <Name>task1</Name>

                                                    <Active>1</Active>

                                                    <Manual>1</Manual>

                                                    <Type>0</Type>

                                                    <IsNull>0</IsNull>

                                                    <CreateDate>2013-12-19T16:42:00</CreateDate>

                                                    <WBS>1</WBS>

                                                    <OutlineNumber>1</OutlineNumber>

                                                    <OutlineLevel>1</OutlineLevel>

                                                    <Priority>500</Priority>

                                                    <Start>2013-12-19T08:00:00</Start>

                                                    <Finish>2013-12-25T17:00:00</Finish>

                                                    <Duration>PT40H0M0S</Duration>

                                                    <ManualStart>2013-12-19T08:00:00</ManualStart>

                                                    <ManualFinish>2013-12-25T17:00:00</ManualFinish>

                                                    <ManualDuration>PT40H0M0S</ManualDuration>

                                                    <DurationFormat>7</DurationFormat>

                                                    <Work>PT40H0M0S</Work>

                                                    <ResumeValid>0</ResumeValid>

                                                    <EffortDriven>0</EffortDriven>

                                                    <Recurring>0</Recurring>

                                                    <OverAllocated>0</OverAllocated>

                                                    <Estimated>0</Estimated>

                                                    <Milestone>0</Milestone>

                                                    <Summary>0</Summary>

                                                    <DisplayAsSummary>0</DisplayAsSummary>

                                                    <Critical>1</Critical>

                                                    <IsSubproject>0</IsSubproject>

                                                    <IsSubprojectReadOnly>0</IsSubprojectReadOnly>

                                                    <ExternalTask>0</ExternalTask>

                                                    <EarlyStart>2013-12-19T08:00:00</EarlyStart>

                                                    <EarlyFinish>2013-12-25T17:00:00</EarlyFinish>

                                                    <LateStart>2013-12-19T08:00:00</LateStart>

                                                    <LateFinish>2013-12-26T08:00:00</LateFinish>

                                                    <StartVariance>0</StartVariance>

                                                    <FinishVariance>0</FinishVariance>

                                                    <WorkVariance>2400000.00</WorkVariance>

                                                    <FreeSlack>0</FreeSlack>

                                                    <TotalSlack>0</TotalSlack>

                                                    <StartSlack>0</StartSlack>

                                                    <FinishSlack>0</FinishSlack>

                                                    <FixedCost>1200</FixedCost>

                                                    <FixedCostAccrual>3</FixedCostAccrual>

                                                    <PercentComplete>%50 </PercentComplete>

                                                    <PercentWorkComplete>0</PercentWorkComplete>

                                                    <Cost>1200</Cost>

                                                    <OvertimeCost>0</OvertimeCost>

                                                    <OvertimeWork>PT0H0M0S</OvertimeWork>

                                                    <ActualDuration>PT0H0M0S</ActualDuration>

                                                    <ActualCost>0</ActualCost>

                                                    <ActualOvertimeCost>0</ActualOvertimeCost>

                                                    <ActualWork>PT0H0M0S</ActualWork>

                                                    <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>

                                                    <RegularWork>PT40H0M0S</RegularWork>

                                                    <RemainingDuration>PT40H0M0S</RemainingDuration>

                                                    <RemainingCost>1200</RemainingCost>

                                                    <RemainingWork>PT40H0M0S</RemainingWork>

                                                    <RemainingOvertimeCost>0</RemainingOvertimeCost>

                                                    <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>

                                                    <ACWP>0.00</ACWP>

                                                    <CV>0.00</CV>

                                                    <ConstraintType>0</ConstraintType>

                                                    <CalendarUID>-1</CalendarUID>

                                                    <LevelAssignments>1</LevelAssignments>

                                                    <LevelingCanSplit>1</LevelingCanSplit>

                                                    <LevelingDelay>0</LevelingDelay>

                                                    <LevelingDelayFormat>8</LevelingDelayFormat>

                                                    <IgnoreResourceCalendar>0</IgnoreResourceCalendar>

                                                    <HideBar>0</HideBar>

                                                    <Rollup>0</Rollup>

                                                    <BCWS>0.00</BCWS>

                                                    <BCWP>0.00</BCWP>

                                                    <PhysicalPercentComplete>0</PhysicalPercentComplete>

                                                    <EarnedValueMethod>0</EarnedValueMethod>

                                                    <IsPublished>1</IsPublished>

                                                    <CommitmentType>0</CommitmentType>

                                    </Task>

     same need to add for resource , for assignment, for TimephasedData then save XML and try. 


    kirtesh

    Thursday, December 19, 2013 3:05 PM
  • Vinayak,

    It sounds like the option for updating tasks is somehow getting set to 0% or 100% complete only either for that task or for the whole project. Note: the options I'm referring to is found under Project/Status group/Update Project icon. I don't know where that option is set in the XML, but you should be able to find it with a simple little test file. Make one run with the option set to 0% or 100% complete only and another run with it set to 0% - 100% complete.

    Hope this helps.

    John

    Thursday, December 19, 2013 4:15 PM
  • Hi John,

    Sorry but I didn't get what you mean. I have 5 tasks in my plan. 2 tasks are 100%,  one 50% and 2 are 0% complete. Below is my generated xml. I cant understand why MS Project keeps changing percent complete when I import it. I am sure I am setting some of the fields wrong, but cant understand which ones.

    <?xml version="1.0"?>
    <Project xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema" xmlns="http://schemas.microsoft.com/project/2010">
      <UID>1</UID>
      <Title>Test project</Title>
      <Subject>Created by P2</Subject>
      <CreationDate>2013-07-18T00:00:00</CreationDate>
      <Revision>1</Revision>
      <StartDate>2013-07-18T00:00:00</StartDate>
      <CriticalSlackLimit>0</CriticalSlackLimit>
      <CurrencyDigits>2</CurrencyDigits>
      <CalendarUID>1</CalendarUID>
      <DefaultStartTime>00:00:00.0000000+00:00</DefaultStartTime>
      <CurrentDate>2013-07-18T00:00:00</CurrentDate>
      <Calendars>
        <Calendar>
          <UID>1</UID>
          <Name>Standard</Name>
          <IsBaseCalendar>true</IsBaseCalendar>
          <BaseCalendarUID>-1</BaseCalendarUID>
          <WeekDays>
            <WeekDay>
              <DayType>1</DayType>
              <DayWorking>false</DayWorking>
            </WeekDay>
            <WeekDay>
              <DayType>2</DayType>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00.0000000+00:00</FromTime>
                  <ToTime>12:00:00.0000000+00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00.0000000+00:00</FromTime>
                  <ToTime>17:00:00.0000000+00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>3</DayType>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00.0000000+00:00</FromTime>
                  <ToTime>12:00:00.0000000+00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00.0000000+00:00</FromTime>
                  <ToTime>17:00:00.0000000+00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>4</DayType>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00.0000000+00:00</FromTime>
                  <ToTime>12:00:00.0000000+00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00.0000000+00:00</FromTime>
                  <ToTime>17:00:00.0000000+00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>5</DayType>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00.0000000+00:00</FromTime>
                  <ToTime>12:00:00.0000000+00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00.0000000+00:00</FromTime>
                  <ToTime>17:00:00.0000000+00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>6</DayType>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00.0000000+00:00</FromTime>
                  <ToTime>12:00:00.0000000+00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00.0000000+00:00</FromTime>
                  <ToTime>17:00:00.0000000+00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>7</DayType>
              <DayWorking>false</DayWorking>
            </WeekDay>
          </WeekDays>
        </Calendar>
      </Calendars>
      <Tasks>
        <Task>
          <UID>0</UID>
          <ID>0</ID>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <CreateDate>2013-12-16T00:00:00</CreateDate>
          <OutlineLevel>0</OutlineLevel>
          <Priority>0</Priority>
          <Duration>PT0H0M0S</Duration>
          <DurationFormat>3</DurationFormat>
          <Work>PT0H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>1</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <StartVariance>0</StartVariance>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <FreeSlack>0</FreeSlack>
          <TotalSlack>0</TotalSlack>
          <FixedCost>0</FixedCost>
          <FixedCostAccrual>1</FixedCostAccrual>
          <PercentComplete>0</PercentComplete>
          <PercentWorkComplete>0</PercentWorkComplete>
          <Cost>0</Cost>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <Manual>0</Manual>
          <ActualDuration>PT0H0M0S</ActualDuration>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualWork>PT0H0M0S</ActualWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingDuration>PT0H0M0S</RemainingDuration>
          <RemainingCost>0</RemainingCost>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <ACWP>0</ACWP>
          <CV>0</CV>
          <ConstraintType>0</ConstraintType>
          <CalendarUID>-1</CalendarUID>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <PhysicalPercentComplete>0</PhysicalPercentComplete>
          <EarnedValueMethod>0</EarnedValueMethod>
          <ActualWorkProtected>PT0H0M0S</ActualWorkProtected>
          <ActualOvertimeWorkProtected>PT0H0M0S</ActualOvertimeWorkProtected>
        </Task>
        <Task>
          <UID>1</UID>
          <ID>1</ID>
          <Name>Hardware Physical or Virtual</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>1</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-07-22T08:00:00</Start>
          <Finish>2013-08-06T17:00:00</Finish>
          <Duration>PT96H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT96H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>1</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-07-22T08:00:00</EarlyStart>
          <EarlyFinish>2013-08-06T08:00:00</EarlyFinish>
          <LateStart>2013-07-22T17:00:00</LateStart>
          <LateFinish>2013-08-06T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>0</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-07-22T08:00:00</ManualStart>
          <ManualFinish>2013-08-06T17:00:00</ManualFinish>
          <ManualDuration>PT96H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-07-22T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>77079393-1B3C-408E-A097-3C7D4295A38C</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <Baseline>
            <Start>2013-07-22T00:00:00</Start>
            <Finish>2013-11-05T00:00:00</Finish>
            <Duration>PT96H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
        </Task>
        <Task>
          <UID>2</UID>
          <ID>2</ID>
          <Name>Setup Webserver</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>2</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-07-22T08:00:00</Start>
          <Finish>2013-07-26T17:00:00</Finish>
          <Duration>PT40H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT40H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-07-22T08:00:00</EarlyStart>
          <EarlyFinish>2013-07-26T08:00:00</EarlyFinish>
          <LateStart>2013-07-22T17:00:00</LateStart>
          <LateFinish>2013-07-26T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>50</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-07-22T08:00:00</ManualStart>
          <ManualFinish>2013-07-26T17:00:00</ManualFinish>
          <ManualDuration>PT40H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-07-22T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>AE541DC9-22F1-4C40-A338-C09CDE17B47C</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <Baseline>
            <Start>2013-07-22T00:00:00</Start>
            <Finish>2013-07-26T00:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
          <TimephasedData>
            <Type>11</Type>
            <UID>2</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>100</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>2</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>100</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>2</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>50</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>2</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>2</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
        </Task>
        <Task>
          <UID>3</UID>
          <ID>3</ID>
          <Name>Setup Website</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>2</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-07-29T08:00:00</Start>
          <Finish>2013-08-01T17:00:00</Finish>
          <Duration>PT32H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT32H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-07-29T08:00:00</EarlyStart>
          <EarlyFinish>2013-08-01T08:00:00</EarlyFinish>
          <LateStart>2013-07-29T17:00:00</LateStart>
          <LateFinish>2013-08-01T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>0</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-07-29T08:00:00</ManualStart>
          <ManualFinish>2013-08-01T17:00:00</ManualFinish>
          <ManualDuration>PT32H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-07-29T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>13453D5E-3273-4214-8B5A-A0D8ADDDA605</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <PredecessorLink>
            <PredecessorUID>2</PredecessorUID>
            <CrossProject>0</CrossProject>
            <LinkLag>0</LinkLag>
            <LagFormat>7</LagFormat>
          </PredecessorLink>
          <Baseline>
            <Start>2013-07-29T00:00:00</Start>
            <Finish>2013-08-01T00:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
          <TimephasedData>
            <Type>11</Type>
            <UID>3</UID>
            <Start>2013-07-29T08:00:00</Start>
            <Finish>2013-07-30T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>3</UID>
            <Start>2013-07-29T08:00:00</Start>
            <Finish>2013-07-30T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>3</UID>
            <Start>2013-07-29T08:00:00</Start>
            <Finish>2013-07-30T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>3</UID>
            <Start>2013-07-29T08:00:00</Start>
            <Finish>2013-07-30T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
        </Task>
        <Task>
          <UID>4</UID>
          <ID>4</ID>
          <Name>Register URL kiabmdashboard.com</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>2</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-07-22T08:00:00</Start>
          <Finish>2013-07-24T17:00:00</Finish>
          <Duration>PT24H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT24H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-07-22T08:00:00</EarlyStart>
          <EarlyFinish>2013-07-24T08:00:00</EarlyFinish>
          <LateStart>2013-07-22T17:00:00</LateStart>
          <LateFinish>2013-07-24T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>0</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-07-22T08:00:00</ManualStart>
          <ManualFinish>2013-07-24T17:00:00</ManualFinish>
          <ManualDuration>PT24H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-07-22T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>4E6004D9-8876-4CB1-A934-25D8A7A73A5E</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <Baseline>
            <Start>2013-07-22T00:00:00</Start>
            <Finish>2013-07-24T00:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
          <TimephasedData>
            <Type>11</Type>
            <UID>4</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>4</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>4</UID>
            <Start>2013-07-22T08:00:00</Start>
            <Finish>2013-07-23T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>0</Value>
          </TimephasedData>
        </Task>
        <Task>
          <UID>5</UID>
          <ID>5</ID>
          <Name>Setup Users for Test Roles</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>2</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-08-02T08:00:00</Start>
          <Finish>2013-08-02T17:00:00</Finish>
          <Duration>PT8H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT8H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-08-02T08:00:00</EarlyStart>
          <EarlyFinish>2013-08-02T08:00:00</EarlyFinish>
          <LateStart>2013-08-02T17:00:00</LateStart>
          <LateFinish>2013-08-02T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>100</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-08-02T08:00:00</ManualStart>
          <ManualFinish>2013-08-02T17:00:00</ManualFinish>
          <ManualDuration>PT8H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-08-02T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>7994499C-81CE-400D-A2E4-D11C234121AE</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <PredecessorLink>
            <PredecessorUID>3</PredecessorUID>
            <CrossProject>0</CrossProject>
            <LinkLag>0</LinkLag>
            <LagFormat>7</LagFormat>
          </PredecessorLink>
          <PredecessorLink>
            <PredecessorUID>4</PredecessorUID>
            <CrossProject>0</CrossProject>
            <LinkLag>0</LinkLag>
            <LagFormat>7</LagFormat>
          </PredecessorLink>
          <Baseline>
            <Start>2013-08-02T00:00:00</Start>
            <Finish>2013-08-02T00:00:00</Finish>
            <Duration>PT8H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
          <TimephasedData>
            <Type>11</Type>
            <UID>5</UID>
            <Start>2013-08-02T08:00:00</Start>
            <Finish>2013-08-03T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>100</Value>
          </TimephasedData>
        </Task>
        <Task>
          <UID>6</UID>
          <ID>6</ID>
          <Name>Test</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OutlineLevel>2</OutlineLevel>
          <Priority>0</Priority>
          <Start>2013-08-05T08:00:00</Start>
          <Finish>2013-08-06T17:00:00</Finish>
          <Duration>PT16H0M0S</Duration>
          <DurationFormat>7</DurationFormat>
          <Work>PT16H0M0S</Work>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2013-08-05T08:00:00</EarlyStart>
          <EarlyFinish>2013-08-06T08:00:00</EarlyFinish>
          <LateStart>2013-08-05T17:00:00</LateStart>
          <LateFinish>2013-08-06T17:00:00</LateFinish>
          <FixedCostAccrual>2</FixedCostAccrual>
          <PercentComplete>100</PercentComplete>
          <Manual>1</Manual>
          <ManualStart>2013-08-05T08:00:00</ManualStart>
          <ManualFinish>2013-08-06T17:00:00</ManualFinish>
          <ManualDuration>PT16H0M0S</ManualDuration>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>1</CalendarUID>
          <ConstraintDate>2013-08-05T08:00:00</ConstraintDate>
          <LevelAssignments>0</LevelAssignments>
          <LevelingCanSplit>0</LevelingCanSplit>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <Notes>37E1D040-EC1E-4978-B8F9-B1F4A27E5549</Notes>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <PredecessorLink>
            <PredecessorUID>5</PredecessorUID>
            <CrossProject>0</CrossProject>
            <LinkLag>0</LinkLag>
            <LagFormat>7</LagFormat>
          </PredecessorLink>
          <Baseline>
            <Start>2013-08-05T00:00:00</Start>
            <Finish>2013-08-06T00:00:00</Finish>
            <Duration>PT16H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
          </Baseline>
          <TimephasedData>
            <Type>11</Type>
            <UID>6</UID>
            <Start>2013-08-05T08:00:00</Start>
            <Finish>2013-08-06T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>100</Value>
          </TimephasedData>
          <TimephasedData>
            <Type>11</Type>
            <UID>6</UID>
            <Start>2013-08-05T08:00:00</Start>
            <Finish>2013-08-06T08:00:00</Finish>
            <Unit>2</Unit>
            <Value>100</Value>
          </TimephasedData>
        </Task>
      </Tasks>
      <Resources>
        <Resource>
          <UID>0</UID>
          <ID>0</ID>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <OverAllocated>0</OverAllocated>
          <CanLevel>0</CanLevel>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
        </Resource>
        <Resource>
          <UID>1</UID>
          <ID>1</ID>
          <Name>Ben Hollins</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <WorkGroup>0</WorkGroup>
          <MaxUnits>0</MaxUnits>
          <PeakUnits>0</PeakUnits>
          <OverAllocated>1</OverAllocated>
          <CanLevel>0</CanLevel>
          <AccrueAt>1</AccrueAt>
          <Work>PT0H0M0S</Work>
          <RegularWork>PT0H0M0S</RegularWork>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <PercentWorkComplete>0</PercentWorkComplete>
          <StandardRate>0</StandardRate>
          <StandardRateFormat>1</StandardRateFormat>
          <Cost>0</Cost>
          <OvertimeRate>0</OvertimeRate>
          <OvertimeRateFormat>1</OvertimeRateFormat>
          <OvertimeCost>0</OvertimeCost>
          <CostPerUse>0</CostPerUse>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <WorkVariance>0</WorkVariance>
          <SV>0</SV>
          <CV>0</CV>
          <ACWP>0</ACWP>
          <CalendarUID>1</CalendarUID>
          <Notes>80b6a839-b2ab-4a98-843d-5bbfffd62ab3</Notes>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
          <BookingType>0</BookingType>
        </Resource>
        <Resource>
          <UID>2</UID>
          <ID>2</ID>
          <Name>Jourii Patoulyak</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <WorkGroup>0</WorkGroup>
          <MaxUnits>0</MaxUnits>
          <PeakUnits>0</PeakUnits>
          <OverAllocated>1</OverAllocated>
          <CanLevel>0</CanLevel>
          <AccrueAt>1</AccrueAt>
          <Work>PT0H0M0S</Work>
          <RegularWork>PT0H0M0S</RegularWork>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <PercentWorkComplete>0</PercentWorkComplete>
          <StandardRate>0</StandardRate>
          <StandardRateFormat>1</StandardRateFormat>
          <Cost>0</Cost>
          <OvertimeRate>0</OvertimeRate>
          <OvertimeRateFormat>1</OvertimeRateFormat>
          <OvertimeCost>0</OvertimeCost>
          <CostPerUse>0</CostPerUse>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <WorkVariance>0</WorkVariance>
          <SV>0</SV>
          <CV>0</CV>
          <ACWP>0</ACWP>
          <CalendarUID>1</CalendarUID>
          <Notes>890878fc-501e-44a6-8980-ada0b9d23120</Notes>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
          <BookingType>0</BookingType>
        </Resource>
        <Resource>
          <UID>3</UID>
          <ID>3</ID>
          <Name>Jason Heath</Name>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <WorkGroup>0</WorkGroup>
          <MaxUnits>0</MaxUnits>
          <PeakUnits>0</PeakUnits>
          <OverAllocated>1</OverAllocated>
          <CanLevel>0</CanLevel>
          <AccrueAt>1</AccrueAt>
          <Work>PT0H0M0S</Work>
          <RegularWork>PT0H0M0S</RegularWork>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <PercentWorkComplete>0</PercentWorkComplete>
          <StandardRate>0</StandardRate>
          <StandardRateFormat>1</StandardRateFormat>
          <Cost>0</Cost>
          <OvertimeRate>0</OvertimeRate>
          <OvertimeRateFormat>1</OvertimeRateFormat>
          <OvertimeCost>0</OvertimeCost>
          <CostPerUse>0</CostPerUse>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <WorkVariance>0</WorkVariance>
          <SV>0</SV>
          <CV>0</CV>
          <ACWP>0</ACWP>
          <CalendarUID>1</CalendarUID>
          <Notes>ae82de5c-013b-471d-8702-e2a1d90a113e</Notes>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
          <BookingType>0</BookingType>
        </Resource>
      </Resources>
      <Assignments>
        <Assignment>
          <UID>0</UID>
          <TaskUID>0</TaskUID>
          <ResourceUID>0</ResourceUID>
          <Confirmed>0</Confirmed>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <ResponsePending>0</ResponsePending>
          <UpdateNeeded>0</UpdateNeeded>
        </Assignment>
        <Assignment>
          <UID>1</UID>
          <TaskUID>2</TaskUID>
          <ResourceUID>1</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-07-26T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-07-22T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-07-26T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-07-22T08:00:00</Start>
          <Stop>2013-07-26T17:00:00</Stop>
          <Resume>2013-07-26T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT40H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
        <Assignment>
          <UID>2</UID>
          <TaskUID>3</TaskUID>
          <ResourceUID>3</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-08-01T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-07-29T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-08-01T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-07-29T08:00:00</Start>
          <Stop>2013-08-01T17:00:00</Stop>
          <Resume>2013-08-01T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT32H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
        <Assignment>
          <UID>3</UID>
          <TaskUID>4</TaskUID>
          <ResourceUID>1</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-07-24T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-07-22T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-07-24T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-07-22T08:00:00</Start>
          <Stop>2013-07-24T17:00:00</Stop>
          <Resume>2013-07-24T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT24H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
        <Assignment>
          <UID>4</UID>
          <TaskUID>5</TaskUID>
          <ResourceUID>2</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-08-02T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-08-02T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-08-02T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-08-02T08:00:00</Start>
          <Stop>2013-08-02T17:00:00</Stop>
          <Resume>2013-08-02T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT8H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
        <Assignment>
          <UID>5</UID>
          <TaskUID>5</TaskUID>
          <ResourceUID>3</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-08-02T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-08-02T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-08-02T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-08-02T08:00:00</Start>
          <Stop>2013-08-02T17:00:00</Stop>
          <Resume>2013-08-02T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT8H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
        <Assignment>
          <UID>6</UID>
          <TaskUID>6</TaskUID>
          <ResourceUID>2</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualFinish>2013-08-06T17:00:00</ActualFinish>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualStart>2013-08-05T08:00:00</ActualStart>
          <ACWP>0</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostVariance>0</CostVariance>
          <CV>0</CV>
          <Delay>0</Delay>
          <Finish>2013-08-06T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>0</WorkVariance>
          <HasFixedRateUnits>0</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>3</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT0H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2013-08-05T08:00:00</Start>
          <Stop>2013-08-06T17:00:00</Stop>
          <Resume>2013-08-06T17:00:00</Resume>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0</VAC>
          <Work>PT16H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0</BCWS>
          <BCWP>0</BCWP>
          <BookingType>0</BookingType>
        </Assignment>
      </Assignments>
    </Project>


    Vinayak Nirvani.

    Thursday, December 19, 2013 4:34 PM
  • Vinayak,

    I'm not that familiar with the XML format so I really don't know where to look but my suggestion for doing a one task test file, (first with the option for 0% OR 100% and second with the option for 0% through 100%), could make the search easier.

    Another question, are you tasks being imported manually scheduled or auto-scheduled? Whichever, try the other scheduling mode and see if that makes a difference.

    John

    Thursday, December 19, 2013 6:29 PM